Nighttime airport road closures coming on Friday, Jan. 30

January 28, 2009

Motorists traveling to and from Sea-Tac International Airport Friday night and early Saturday need to allow extra time due to road closures. Contractors building the Link light rail station at the airport will erect a pre-fabricated steel pedestrian bridge spanning International Boulevard and the northbound Airport Expressway lanes. The work will require temporary overnight closures of both roadways.

A 550-ton crane with a 116-foot boom will work in the median of International Boulevard to set the bridge in place.

The new pedestrian bridge will connect SeaTac/Airport Station with a new pick-up/drop-off area on the east side of International Boulevard.

What travelers can expect: 

Northbound International Boulevard detour:

Southbound International Boulevard detour:

Airport Expressway detour:

For more information on traffic detours please see: http://www.portseattle.org/seatac/traveler/roads.shtml

Drivers traveling to and from Sea-Tac Airport should allow extra time for delays during these periods and of course drive cautiously and pay close attention to flaggers and detour signage.

The schedule for this work is subject to change if necessary. The latest schedule information is posted at http://www.soundtransit.org/projectupdates

For more information on SeaTac/Airport Station please see:

http://www.soundtransit.org/x1669.xml