 ST Express Regional Bus - Redondo Heights Park-and-Ride/SR-99Description
The Redondo Heights Park-and-Ride/SR 99 project provides a new 700 stall surface park-and-ride at the northeast corner of the intersection of Pacific Highway South (SR-99) and South 272nd Street. The project features a bus loading area that accommodates three buses and a layover area that can hold up to four buses. Also included in the project are three bus shelters, a new traffic control signal and landscaping along three boundaries. King County Metro served as the construction lead on the project. Sound Transit led the initial phases of the project completing preliminary engineering and environmental documentation.
| Location: |
|
Pacific Highway South (SR-99), just south of South 272nd Street
|
| |
| Jurisdiction: |
|
City of Federal Way
|
| |
| Facility Type: |
|
Park-and-ride lot
|
| |
| Sound Transit Budget: |
|
$2.4 million
|
| |
| Partners: |
|
Sound Transit
City of Federal Way
King County Metro Transit (Metro)
|
| |
| Consultants: |
|
Preliminary Engineering/Environmental Documentation: Sverdrup Civil Inc.
Final Design/ Construction management: Metro
Construction: SCI Infrastructure, LLC
|
| |
| Project Organization: |
|
Federal Way Project Management Team: Sound Transit, WA State Department of Transportation (WSDOT), Cities of Kent and Federal Way, Metro and Pierce Transit
Federal Way Executive Advisory Committee: Sound Transit, WSDOT, Cities of Kent and Federal Way, Metro, Pierce Transit, Federal Transit Administration, Federal Highway Administration and community representatives
|
| |
| Project Timeline: |
|
Preliminary engineering and environmental documentation completed: June 2001
Final design completed: December 2002
Construction began: November 2003
Construction completed: April 2005
|