85th Corridor/Related ImprovementsDescription
This is one of three projects in Kirkland. The Kirkland Transit Enhancements project includes a variety of improvements along ST Express Route 540 to increase access, reliability and operating speed.
Project Facts
| Location: |
|
Various sections of ST Express Route 540 from Redmond Downtown to SR-520
|
| |
| Sound Transit Budget: |
|
$8.4 million
|
| |
| Planning Partners: |
|
City of Kirkland
City of Redmond
City of Bellevue
WA State Dept of Transportation
King County Metro (providing transit services and operates on-board signal priority equipment)
|
| |
| Consultants and Contractors: |
|
Preliminary Engineering/Environmental Documentation: David Evans & Associates
Final Design: David Evans & Associates
Construction: TBD
|
| |
| Project Timeline: |
|
Sound Transit Board approved of the engineering contract: First Quarter of 2002
Construction: Expected from 2nd quarter 2006 through 1st quarter 2008
|
Project Contact
If you have questions about this project, please contact:
Roger Iwata Community Outreach Specialist
Phone:(206) 689-4904 roger.iwata@soundtransit.org
For more information about Sound Transit....... Contracting opportunities? Bus and train service? Contact us at: main@soundtransit.org
Submit Project Feedback
|
Copyright 2006, Sound Transit