Issaquah Transit Center/SR-900Description
The Issaquah Transit Center project provides a new transit center at the site of the existing Issaquah Park-and-Ride at State Route 900 and Newport Way N.W. The new transit center features over 800 parking stalls in a garage, bus layover space, six new bus bays with efficient loading areas, and weather-protected passenger shelters. The secure facility includes CCTV, customer emergency stations, a security office and police outpost. A passenger pick up/drop off area, bicycle storage, public art and rain gardens are also elements of project.
Construction Alert: Issaquah Park-and-Ride bus area moves March 24, 2007
Construction Alert: Issaquah Park-and-Ride closed June 3, 2006
Project Facts
| Location: |
|
SR 900 between Newport Way NW and NW Maple St.
|
| |
| Sound Transit Budget: |
|
$29.5 million
|
| |
| Planning Partners: |
|
City of Issaquah
King County Metro
|
| |
| Consultants and Contractors: |
|
KPFF Consulting Engineers for preliminary engineering, environmental documentation and final design
Gordon Huether, public art
Harris and Associates, construction management
Harbor Pacific Contractors, Inc for construction
|
| |
| Project Timeline: |
|
Environmental Review and Preliminary Design Completed: October 2004
Final Design Completed: December 2005
Construction Began: June 2006
Expected to Open for Service: Summer, 2008
|
Project Contact
If you have questions about this project, please contact:
Roger Iwata Community Outreach Specialist
Phone:(206) 689-4904 roger.iwata@soundtransit.org
For more information about Sound Transit....... Contracting opportunities? Bus and train service? Contact us at: main@soundtransit.org
Submit Project Feedback
|
|

Photos & drawings for this project >>>
|