Issaquah Transit Center/SR-900Description
The Issaquah Transit Center project provides a new transit center at the site of the existing Issaquah Park-and-Ride at State Route 900 and Newport Way N.W. The transit center features 819 parking stalls in a four-story garage, bus layover space, six new bus bays with efficient loading areas, and weather-protected passenger shelters. The secure facility includes CCTV, customer emergency stations, and a police outpost. A passenger pick up/drop off area, bicycle storage, and public art are also elements of project.
Rider information for this facility >>>
Project Facts
| Location: |
|
SR 900 between Newport Way NW and NW Maple St.
|
| |
| Sound Transit Budget: |
|
$29.5 million
|
| |
| Planning Partners: |
|
City of Issaquah
King County Metro
|
| |
| Consultants and Contractors: |
|
KPFF Consulting Engineers for preliminary engineering, environmental documentation and final design
Gordon Huether, public art
Harris and Associates, construction management
Harbor Pacific Contractors, Inc for construction
|
| |
| Project Timeline: |
|
Environmental Review and Preliminary Design Completed: October 2004
Final Design Completed: December 2005
Construction Began: June 2006
Open for Service (transit island): May, 2008
Open for Service (parking garage): July, 2008
|
Questions about Sound Transit?
Contact us
|
|

Photos & drawings for this project >>>
|
Copyright 2006, Sound Transit