Kirkland Transit Center
Update: Environmental Documentation Complete for Kirkland Transit Center Enhancement Project
Sound Transit has completed the environmental review and documentation process under the State Environmental Policy Act (SEPA) for the Kirkland Transit Center project. A SEPA Checklist and SEPA Addendum were prepared and a detailed noise study was conducted. Sound Transit issued a Determination of Nonsignificance (DNS) under SEPA on May 12, 2008. The SEPA documents and noise study are available for review. Please see the links on this page to the various environmental documents/determinations related to this project.
SEPA Environmental Checklist -- January 10, 2008 (PDF, 5.9 mb)
SEPA Addendum -- May 8, 2008 (PDF, 2 mb)
Noise Technical Report -- May 2008 (PDF, 438 kb)
Noise Technical Report Figures -- May 2008 (PDF, 4 mb)
SEPA Determination of Nonsignificance -- issued May 12, 2008 (PDF, 122 kb)
Notice of DNS to Recipients -- May 9, 2008 (PDF, 145 kb)
Formal comments may be submitted by 5:00 p.m. on May 27, 2008 to:
Perry Weinberg
Sound Transit, Environmental Compliance Manager
Office of Legal Affairs
401 South Jackson St.
Seattle, WA 98104-2826
Description
The Kirkland Transit Center project provides a new transit center on 3rd Street between Central Way and Kirkland Avenue. The project will transform the existing twenty-two-year old facility, improving speed and reliability of bus service, and providing new waiting areas, passenger shelters, and enhanced pedestrian crossings. Signal, intersection, and traffic circulation improvements will increase pedestrian safety while also smoothing traffic flows in the area.
Bicycle amenities, landscaping and public art are also elements of the project.
Project Facts
| Location: |
|
3rd Street between Central Way and Kirkland Avenue
|
| |
| Sound Transit Budget: |
|
$13.3 million
|
| |
| Planning Partners: |
|
City of Kirkland
King County Metro
|
| |
| Consultants and Contractors: |
|
INCA Engineers Inc. for preliminary design and environmental review
Public Art: Carolyn Law
|
| |
| Project Timeline: |
|
Environmental review is expected to be finished Summer 2008;
Final design is scheduled to be completed early 2009;
Construction is expected to be completed in 2010.
|
| |
Project Contact
If you have questions about this project, please contact:
Roger Iwata Community Outreach Specialist
Phone:(206) 689-4904 roger.iwata@soundtransit.org