Tacoma Dome Station - Parking
Description
This project funded Phase II expansion of the Tacoma Dome Station parking structure to provide additional parking capacity for customer access to ST Express, Pierce Transit services, Sounder Commuter Rail and Link Light Rail services.
Rider information for this facility>>>
| Progress Report: |
|
Completed in 2000
|
| |
| Location: |
|
Adjacent to the Tacoma Dome Station
|
| |
| Jurisdiction: |
|
City of Tacoma
|
| |
| Facility Type: |
|
Phase I: Transit center and 1200 stall parking garage
Phase II: Additional 1200 stall parking garage
|
| |
| Sound Transit Budget: |
|
$11.12 Million per Phase II
|
| |
| Partners: |
|
Pierce Transit
|
| |
| Consultants: |
|
Preliminary Engineering/Environmental Documentation Consultant: Design consultant Berger Abam
Construction contractor (GCCM): Absher Construction - Phase II
|
| |
| Contractor: |
|
Tri-State Construction
|
| |
| Project Organization: |
|
Memorandum of Agreement with Pierce Transit identifies reporting, invoicing and other requirements
|
| |
| Project Timeline: |
|
Phase I completed and operational: October 1997
Construction began: May 1999
Construction completed: Fall 2000
|
Questions about Sound Transit?
Contact us
|
Copyright 2006, Sound Transit