Full closure of 48th Ave W

As early as Thursday, March 21, Sound Transit’s contractor will continue installing a storm crossing on 48th Ave W. This will require the full closure of 48th Ave W south of 200th St SW. Access to…

Nightly closure of 5th Ave NE and northbound I-5 on-ramp

Starting Wednesday, March 13, Sound Transit will close 5th Ave NE between NE 145th St and NE 148th St for striping realignment. This road closure will also affect the northbound I-5 on-ramp from NE…

Night closure of northbound I-5 on-ramp and right lane

On Thursday, March 14, Sound Transit will close the northbound I-5 on-ramp from NE 145th St and the northbound I-5 right lane from NE 145th St to NE 155th St for barrier removal. This work is part of…

Nightly closures at SR 104 interchange

As early as Monday, March 11, Sound Transit’s contractor will auger, form, prep, and pour light pole foundations at the SR 104 interchange in Shoreline. This work will require periodic nightly…

Full closure of 46th Ave W

As early as Monday, March 11, Sound Transit’s contractor will continue working on pavement markings at 46th Ave W. This will require the closure of 46th Ave W south of 200th St SW and the HOV ramp…

Northbound I-5 to King County Metro off-ramp closure

On Thursday, March 7, Sound Transit will close the northbound I-5 to King County Metro North Base off-ramp for landscape restoration work at NE 161st St. This work is a part of the Lynnwood Link…

Nightly closure of northbound I-5 on-ramp from NE 175th St

Starting Tuesday, March 5, Sound Transit will close the NE 175th St to northbound I-5 on-ramp for landscape restorations at NE 183rd St. This work is part of the Lynnwood Link Extension.

Night closure of northbound I-5 right lanes and coinciding ramp closures

Starting Monday, March 4, Sound Transit will close the northbound I-5 on-ramp from NE 175th St, the right lane of northbound I-5 between NE 175th St and NE 200th St, and the northbound I-5 off-ramp…

Nightly lane restrictions on NE 145th St (WA-523)

Continuing Sunday, March 3, Sound Transit will be performing waterline work causing nighttime lane restrictions on both eastbound and westbound NE 145th St (WA-523) from 3rd Ave NE to 8th Ave NE. The…

Night work along I-5 in Mountlake Terrace

As early as Friday, March 1, Sound Transit’s contractor will perform night work on I-5 in Mountlake Terrace. This work will include median filter drain installation, metal beam guardrail installation…