Project updates
Learn about where and when construction is happening throughout the ST district.

Non-concurrent nighttime closures of NE 103rd and NE 100th streets

Publish Date
Body

Next Monday and Tuesday nights, April 10th and 11th, crews will move two cranes across Northeast 103rd and Northeast 100th streets near the intersections of 1st Avenue Northeast.

Map of temporary road closures at Northgate Station construction site.

The cranes are a key component of drilled shaft work underway in advance of installation of the columns that will support the future elevated guideway and station at this location.

Northeast 103rd and Northeast 100th streets will not be closed concurrently. One of these streets will remain open to through traffic while the other is temporarily closed.

No high impact noise activities (such as jackhammering or saw-cutting) will take place after 10 p.m. Access to homes, businesses, Northgate Mall and the Northgate Transit Center will be maintained.