Lane closure: Banner Way NE & NE 76th & NE 78th Street

Publish Date
Body

As early as Thursday, June 29, Sound Transit's contractor will close a lane on Banner Way Northeast to proceed with the restoration of Banner Way NE. The construction and traffic impacts will take place in two locations and are listed below (see map).

Map of lane closures on Banner Way Northeast.

What to expect:

Banner Way Northeast and Northeast 76th Street

Traffic impacts: Southbound left lane closure on Banner Way Northeast in the work area. Pedestrian, bicyclist, and motorist traffic will be maintained. Street parking may be impacted during this work.

Construction activities: Sawcutting, and removal of concrete. Pouring new concrete. Once poured concrete will take 72 hours to cure.

Equipment: Concrete, construction trucks, and support equipment.

Work hours: 7 a.m. to 5:30 p.m. Monday to Friday

Duration: June 29 – July 21

Banner Way Northeast and Northeast 78th Street

Traffic impacts: Southbound left lane closure on Banner Way Northeast in the work area. Pedestrian, bicyclist and motorist traffic will be maintained. Street parking may be impacted.

Construction activities: Sawcutting and removal of concrete. Pouring new concrete. Once poured concrete will take 72 hours to cure. Contractor will return at a later date to install ADA ramps.

Equipment: Concrete, construction trucks and support equipment.

Work Hours: 7 a.m. to 5:30 p.m. Monday to Friday

Duration: July 6 – July 26