Upcoming work activities include:

  • April 21 - May 30: Drainage crews will work overnight from 6 p.m. to 2 a.m. for several weeks near East 26th Street and Freighthouse Square.
    • Impacts: Overnight work; no road closure needed.
  • April 22: Crews will replace rail between East 'G' and 'D' Streets.
    • Impacts: One lane may be closed on East 'D' Street. Flaggers will be present.
  • April 28 - May 1: East 'D' Street will be closed to vehicles and pedestrians at the train tracks from the afternoon of April 28 to the morning of May 1.
    • Impacts: Weekend closure of East 'D' Street at the train tracks. East 26th St will be open to pedestrians during this work.

Ongoing work activities include:

  • Construction of the south platform continues along the embankment on the far side of the second tracks.
  • For safety reasons, the intersection of East 26th/East 'G' Street remains closed to pedestrians and vehicles, except for April 28 - May 1.
  • Pile driving for the construction of the south bridge continues.