Construction map for 5th Ave Pedestrian Path re-opening, Lynnwood Link Extension

5th Avenue reopening at NE 185th Street in Shoreline

The 5th Avenue NE realignment section from NE 183rd Court to NE 185th Street is open as of January 7th, 2022.

What

During the closure, Sound Transit contractors completed the following work:

  • Storm and water drain installation
  • Converted overhead power to underground utilities
  • Re-aligned 5th Avenue NE for the future guideway to be constructed
  • Built a retaining wall

Where

  • South portion of NE 185th Street at Interstate 5, and 5th Avenue NE between NE 185th Street and NE 180th Street
  • 5th Avenue NE will be open to through traffic between NE 180th Street and NE 183rd Court; no pedestrian traffic is available at this time
  • NE 185th Street remains open across I-5 to alternating one-way traffic.

More information

The multi-pedestrian path is not completed and will open later. Sound Transit is continuing construction on the west side of 5th Ave from NE 180th Street to NE 185th Street.

Contact us

Community Engagement: my.nguyen@soundtransit.org or 206-370-5690
After-hours construction hotline: 888-298-2395

More updates


Your safety is our priority

Learn how to stay safe around our construction sites.

Stay safe

24-hour construction hotline: 888-298-2395

More project info: soundtransit.org/lle
Get in touch: my.nguyen@soundtransit.org or 206-370-5690