Construction map for work along Martin Luther King Jr Way from South 9th Street to South 6th Street, Hilltop Tacoma Link Extension

Curb and gutter and paving continue along the route

Crews continue installing curb and gutter on Martin Luther King Jr. Way, Division Avenue and Commerce St. Because of stormy weather, some concrete work and paving was rescheduled. The contractor plans to complete this work on Commerce St. from S. 7th St. to I-705 and open this area on Nov. 19. Crews found an underground storage tank on Commerce St. south of S. 7th St., and will address that issue before resuming curb and gutter work on Commerce St. south of S. 7th St. The contractor plans to complete the curb and gutter work on the west side of MLK Jr. Way from S. 10th St. to S. 13th St. by Nov. 20, and open MLK Jr. Way to two-way traffic in this area. Crews tentatively scheduled the paving for the middle of Stadium Way on Nov. 17. In the meantime, Stadium Way is open to two-way traffic.

Crews continue installing signals in the Division Avenue and Yakima Avenue intersection and continue the overhead wire work on MLK Jr. Way and Division Ave. at night.  The contractor plans to install signals in the Division Avenue and I St. intersection as soon as Nov. 15. Two-way traffic will be maintained in these areas.

What

Construction and traffic restrictions at Commerce Street, S. 7th Street, Division Avenue, Martin Luther King Jr. Way, and E. 25th Street.

When

Week of November 12

Where

  • Commerce Street from S. 7th St. to I-705 – northbound lane closure.
  • S. 7th Street at Commerce Street – intersection closed.
  • Division Avenue from MLK Jr. Way to Yakima Ave – traffic restrictions.
  • Martin Luther King Jr. Way from S. 8th St. to 6th Ave – northbound lane closure.
  • Martin Luther King Jr. Way from S. 11th St. to Earnest Brazill St. – southbound lane closure.
  • E. 25th Street from E. G St. to E. J St. – eastbound lane closure.

More

  • Driveway and pedestrian access is maintained, although some sidewalks and crosswalks will be temporarily closed. Pedestrian detours will be in place.
  • Buses will follow detour routes. Visit PierceTransit.org for information.
  • Construction noise related to removing pavement and operating equipment.
  • Large construction equipment or materials may be in the right-of-way.
  • Work will generally take place during the daytime hours unless otherwise noted. Daytime hours during the week are 7 a.m. to 9 p.m. The contractor usually works less hours.
  • Businesses are open during construction.
  • Plan ahead and allow extra time to reach your destination.
  • Due to inclement weather or unforeseen issues, dates and times are subject to change.

Contact us

Community Engagement: liz.ellis@soundtransit.org or 253-208-0586
After-hours construction hotline: 888-298-2395

More updates


Your safety is our priority

Learn how to stay safe around our construction sites.

Stay safe

24-hour construction hotline: 888-298-2395

More project info: soundtransit.org/htlink
Get in touch: liz.ellis@soundtransit.org or 253-208-0586