Construction alert: Hilltop Tacoma Link Extension

Having trouble viewing this email? View it as a Web page.

Construction alert

Map showing traffic impacts for wire installation.

Installing wires over the tracks on MLK Jr. Way from S. 8th St. to Division Ave and then to Yakima Ave starts Oct. 18 at night

Starting this evening, Oct. 18, crews will install the wires over the tracks on Martin Luther King Jr. Way from S. 8th St. to Division Ave, continuing on Division Ave to Yakima Ave. To minimize impacts to the community, this work will happen at night from about 7 p.m. to 6 a.m. To allow space for workers near the Link power poles, parking will not be available on either side of the street at night. Two-way traffic will generally be maintained on Division Ave and MLK Jr. Way. This work will take about four-five weeks.

On Wed, Oct. 20 crews will deliver the building for the traction power substation on N. 2nd St. This work will close N. 2nd St. between N. I St. and Yakima Ave, starting at 7 a.m. on Oct. 20. Parking will not be available near this work. This power building will arrive on a large truck that may travel slowly on Division Ave. The truck route will be SR 16 to Sprague to Division Ave to N. I St. If you travel on Division Ave, please consider another route and allow extra time to reach your destination in the 6 – 7 a.m. timeframe on Oct. 20 – thank you.

On Stadium Way, the contractor is preparing to pave the east side of Stadium Way and plans to lay asphalt on Oct. 21 and 22, depending on weather. In addition, crews are installing curb and gutter on the south side of Division Avenue (the Wright Park side) from MLK Jr. Way to Yakima Ave.

On Martin Luther King Jr. Way, crews are installing curb and gutter in three areas: on the west side of MLK Jr. Way from S. 19th St. to S. 16th St. and from S. 13th St. to S. 10th St., and on the east side from S. 9th St. to 6th Ave. In addition, the contractor is building the St. Joseph and Hilltop District stations.

On Commerce Street, crews continue to work on curb, gutter, paving and the Old City Hall Station. This work is expected to continue until Nov. 9. On E. 25th Street, work is temporarily on hold as the contractor prepares to restore the street; paving is tentatively scheduled for Oct. 25.

What

Construction and traffic restrictions at Commerce Street, S. 7th Street, Stadium Way, Division Avenue, N. 2nd Street, Martin Luther King Jr. Way, S. 16th Street, S. 17th Street, and E. 25th Street.

When

Week of Oct. 18

Where

  • Commerce Street from I-705 to S. 9th St. – southbound lane closure.
  • S. 7th Street at Commerce Street – no left-turn.
  • Stadium Way from Broadway to I-705 – southbound lane closure. Please follow the detour on St. Helens to Market Street, Tacoma Avenue or Broadway.
  • N. 2nd St. from N. I St. to Yakima Ave – street closure on Oct. 20.
  • Division Avenue from MLK Jr. Way to Yakima Ave – traffic restrictions.
  • Martin Luther King Jr. Way from S. 9th St. to 6th Ave – traffic restrictions.
  • Martin Luther King Jr. Way from S. 11th St. to Earnest Brazill St. – southbound lane closure.
  • Martin Luther King Jr. Way from S. 19th St. to S. 15th St – southbound lane closure.
  • S. 16th St. west of Martin Luther King Jr. Way to the alley – intersection closed.
  • S. 17th St. west of Martin Luther King Jr. Way to the alley – intersection closed.
  • E. 25th Street from E. G St. to E. J St. – eastbound lane closure.

More

  • Driveway and pedestrian access is maintained, although some sidewalks and crosswalks will be temporarily closed. Pedestrian detours will be in place.
  • Buses will follow detour routes. Visit PierceTransit.org for information.
  • Construction noise related to removing pavement and operating equipment.
  • Large construction equipment or materials may be in the right-of-way.
  • Work will generally take place during the daytime hours unless otherwise noted. Daytime hours during the week are 7 a.m. to 9 p.m. The contractor usually works less hours.
  • Businesses are open during construction.
  • Plan ahead and allow extra time to reach your destination.
  • Due to inclement weather or unforeseen issues, dates and times are subject to change.

Contact us

Outreach Specialist: liz.ellis@soundtransit.org or 253-208-0586
After-hours construction hotline: 888-298-2395

More updates


Your safety is our priority

Learn how to stay safe around our construction sites.

Stay safe

24-hour construction hotline: 888-298-2395

More project info: soundtransit.org/htlink
Get in touch: liz.ellis@soundtransit.org or 253-208-0586