Construction alert

Map of construction and traffic restrictions

Lane closures on Division Avenue, N. 1st St., and Stadium Way for overhead wire work this week at night

Crews will make some adjustments to the overhead wires on Division Avenue, N. 1st St., and Stadium Way. To minimize impacts to businesses and the traveling public, this work will happen at night this week with some lane closures:

  • Division Avenue – April 25 and 26 from 9 p.m. to 5:30 a.m. Eastbound traffic on Division Ave. will be closed from I St. to Yakima Ave. Please follow the detour on S. I St. to 6th Ave. to Tacoma Ave.
  • N. 1st St. – April 26 and 27 from 10 p.m. to 6 a.m. N. 1st St. will be closed to thru-traffic in both directions from Tacoma Ave. to Yakima Ave. at night.
  • Stadium Way – April 28 and May 2-5 from 9 p.m. to 5:30 a.m. Stadium Way will be closed to southbound traffic from Broadway to I-705 at night. Please follow the detour on Tacoma Ave, St. Helens and Broadway.

In Hilltop, the contractor will start installing a crosswalk at S. 16th St. on the east side of MLK Jr. Way later this week, will continue working on the St. Joseph Station, and will pave the center of MLK Jr. Way when weather permits. On Division Ave, crews are trimming trees and will turn on the signals at Division and I St. this week.

Crews are installing curb and gutter on the west side of MLK Jr. Way near Tacoma General Hospital, and MLK Jr. Way is closed to southbound traffic from S. 3rd St. to 5th St. Access is open to hospitals, the emergency department and medical centers. To access the Baker Center, please follow 6th Avenue to S. L St. To access the hospitals and emergency department, please follow MLK Jr. Way north from 6th Avenue. To enter the emergency department, follow 5th St. down the hill and then exit through the alley to 6th Ave. Please allow a little extra time to reach your appointment – thank you. The traveling public should follow the detour on S. J St.

Looking ahead, the contractor plans to install curb, gutter and sidewalks on the west side of Commerce St. south of S. 7th St. as soon as May 3.

What

Construction and traffic restrictions at Stadium Way, N. 1st Street, N. 2nd St., Division Avenue, Martin Luther King Jr. Way, S. 8th Street, S. 16th Street

When

Week of April 25

Where

  • Stadium Way from Broadway to I-705 – southbound lane closure on April 28 and May 2-5 at night.
  • N. 1st Street from Tacoma Avenue to Yakima Avenue – street closure on April 26-27 at night.
  • N. 2nd Street from Yakima Ave to the alley – street closure.
  • Division Avenue from I St. to Yakima Ave – eastbound lane closed on April 25-26 at night.
  • Martin Luther King Jr. Way from 6th Avenue to S. 3rd St. – southbound lane closure from S. 3rd St. to 5th St.
  • S. 8th Street from Martin Luther King Jr. Way to S. L St. – street closure.
  • Martin Luther King Jr. Way from S. 15th St. to S. 9th St. – traffic restrictions.
  • S. 16th Street east of MLK Jr. Way for about a half block – street closure.
  • Martin Luther King Jr. Way from S. 17th St. to S. 19th St. – southbound lane closure.


More

  • Driveway and pedestrian access is maintained, although some sidewalks and crosswalks will be temporarily closed. Pedestrian detours will be in place.
  • Buses will follow detour routes. Visit PierceTransit.org for information.
  • Construction noise related to removing pavement and operating equipment.
  • Large construction equipment or materials may be in the right-of-way.
  • Work will generally take place during the daytime hours unless otherwise noted.
  • Daytime hours during the week are 7 a.m. to 9 p.m. The contractor usually works less hours.
  • Businesses are open during construction.
  • Plan ahead and allow extra time to reach your destination.
  • Due to inclement weather or unforeseen issues, dates and times are subject to change.

Contact us

Community Engagement: liz.ellis@soundtransit.org or 253-208-0586
After-hours construction hotline: 888-298-2395

More updates


Your safety is our priority

Learn how to stay safe around our construction sites.

Stay safe

24-hour construction hotline: 888-298-2395

More project info: soundtransit.org/htlink
Get in touch: liz.ellis@soundtransit.org or 253-208-0586