As early as Thursday, December 1st, Sound Transit will be closing NE 185th St. from 5th Ave NE to 8th Ave NE for a concrete pour on the NE 185th St. undercrossing. This work is part of the future Lynnwood Link Extension link light rail project.
What:
- Sound Transit will be performing this work at night due to road closure restrictions to reduce traffic delays.
- Neighbors may be affected by noise from a concrete truck, pump truck, forklift, manlift and light plants.
- Will consist of 1 working night from dates below to complete this work. Work is weather dependent and may be moved or adjusted to the noted backup dates. If the work is delayed beyond the provided dates, a new night road closure will be schedule and a new flyer will be provided to residents.
When:
-
Thursday, Dec. 1st from 10 p.m. – 6 a.m. the following morning
-
Saturday, Dec. 3rd from 10 p.m. – 6 a.m. the following morning (Backup Date)
-
Monday, Dec. 5th from 10 p.m. – 6 a.m. the following morning (Backup Date)
Where:
- NE 185th St. between 5th Ave NE and 8th Ave NE, just east of Interstate I-5.
- Detour routes are in place (see map).
Contact us
Community Engagement: c-jaybee.ragudo@soundtransit.org or 206-701-1469 After-hours construction hotline: 888-298-2395
Learn how to stay safe around our construction sites.
|