RESCHEDULED: Weekend closures of 112th Ave SE

Publish Date

Construction crews are rescheduling this construction activity, originally scheduled for Sept. 26 and 27, to Oct. 3 and 4.

As crews continue repaving sections of 112th Avenue Southeast, they will be closing 112th Avenue Southeast between the Y intersection and Southeast 8th Street on Saturday, Oct. 3 and Sunday, Oct. 4. 

This work will be done under an extended work permit which allows crews to work between 7 a.m. and 9 p.m. 

Access to Bellefield Residential Park and emergency services will be maintained.

When

7 a.m. Saturday, Oct. 3 to 9 p.m. Sunday, Oct. 4.

Where

112th Southeast between the Y intersection and Southeast 8th Street.

More

  • Bellefield Residents and guests will be able to access the residential park from Bellevue Way Southeast 
  • Detours:
    • From I-405 travel north on 112th Avenue Southeast to Main Street. Turn right on Main Street and travel west to Bellevue Way. Turn left on Bellevue Way to travel south.
    • From I-90 travel north on Bellevue Way to Main Street. Turn right on Main Street and travel east to 112th Avenue Southeast. Turn left on 112th Avenue Southeast to travel south
  • Plan ahead, leave early and allow extra time to reach your destination.
  • Due to inclement weather or unforeseen issues, dates and times are subject to change.