During construction - South Bellevue Station

Update your subscriber preferences today to receive area-specific updates that include advanced notification for traffic impacts, new construction activities and more. The current construction schedule is below and is subject to change as construction contracts are awarded.

2018 East Link construction milestones include:

  • The Rainier Freeway station and D2 bus roadway from I-90 into downtown Seattle will close in the fall for work on the Judkins Park station.
  • Construction starts on the Operations and Maintenance Facility: East (OMF East) in Bellevue.
  • Elevated rail guideway is placed over I-405 in Bellevue.
  • Excavation of the downtown Bellevue tunnel is completed.
  • Post-tensioning of the I-90 floating bridge to prepare it for light rail and increase its lifespan is completed.
  • Road-over-rail undercrossing on 112th Avenue Southeast in Bellevue gets started.
  • Work proceeds on station construction across the entire East Link extension.