Correction: Federal Way Downtown Traffic Control updates for S 320th St., S 317th St. and 21st Avenue
* The previous iteration of this email included an incorrect set of dates for the S 317th weekend full closure. Please refer to this email for the correct dates.
Sound Transit crews will conduct a series of utility and signal installations in downtown Federal Way throughout October. Travelers through downtown Federal Way should be aware of periodic traffic effects around the Federal Way Transit Center. Sound Transit will continue to advance construction in Federal Way ahead of the upcoming holiday season. Please follow all signed detours.
Sound Transit crews will support access to all businesses near this work, so let’s be Loyal to the Local!
S 317th Street weekend full closure
What
Utility crossings across S 317th Street.
Where
S 317th Street, between 23rd Avenue South and the entrance to the Chelsea Court Condominiums.
When
Starting as early as 7 a.m. on October 21 around the clock until 5 p.m. on October 22
Single lane closure on S 320th Street
What
Storm drain installations and utility tie-ins.
Where
The far right lane of westbound S 320th Street, between 21st Avenue S and 23rd Avenue S.
When
Nightly, from 10 p.m. to 5 a.m., starting on Sunday, Oct. 22 until Thursday, Oct. 26.
Full closure of 21st Avenue S for crane removal
What
Disassembly and removal of a tower crane on the west side of the Federal Way Transit Center.
Where
21st Avenue S, running alongside the Federal Way Transit Center.
When
All day, starting at 7 a.m. on Wednesday, Nov. 1, until 5 p.m. on Friday, Nov. 3.*
*All work is weather dependent, and dates are subject to change