Construction alert: Hilltop Tacoma Link Extension

Having trouble viewing this email? View it as a Web page.

Construction alert

Construction map for Stadium Way Closure, Hilltop Tacoma Link Extension

Stadium Way to open temporarily on Sept. 17

Crews plan to complete the curb, gutter and track work on the west side of Stadium Way by the end of the day on Friday, Sept. 17. Then, Stadium Way will open to two-way traffic. Stadium Way will be open during the Stadium Art, Wine and Beer Walk on Saturday, Sept. 18. However, Stadium Way will close to southbound traffic again on Wed, Sept. 22 when crews start to mill and pave the street. During the southbound Stadium Way closure this week, please follow the St. Helens to Market Street detour to access downtown and I-705. To access northbound Stadium Way, please follow Commerce St. from S. 9th St. or take the I-705 exit – thank you.

On Martin Luther King Jr. Way, crews are installing curb and gutter on the east side of MLK Jr. Way from S. 13th St. to S. 10th St. and on the west side of MLK Jr. Way from S. 19th St. to S. 16th St., including building the St. Joseph Station. In addition, crews are installing the wires over the tracks on MLK Jr. Way from S. 16th St. to S. 8th St. at night. This week, the contractor will finish the temporary signal work at the Division Avenue and MLK Jr. Way intersection, and may move to the S. 15th St. and MLK Jr. Way intersection.

On Commerce Street, crews are installing track, curb, gutter, paving and the platform for the Old City Hall Station. On E. 25th Street, crews are installing track, curb, gutter, and paving.

Looking ahead, the contractor plans to install signals at the Tacoma Avenue and N. 1st St. intersection on Sept. 21 and start paving Stadium Way as soon as Sept. 22.   

What

Construction and traffic restrictions at Commerce Street, S. 7th Street, Stadium Way, Division Avenue, Martin Luther King Jr. Way, and E. 25th Street.

When

Week of September 13

Where

  • Commerce Street from I-705 to S. 9th – southbound lane closure.
  • 7th Street at Commerce Street – no left-turn.
  • Stadium Way from Broadway to I-705 – southbound lane closed. Please follow the detour on St. Helens to Market Street, Tacoma Avenue or Broadway.
  • Division Avenue and Martin Luther King Jr. Way intersection – traffic restrictions.
  • Martin Luther King Jr. Way from S. 13th to S. 10th St. – traffic restrictions.
  • Martin Luther King Jr. Way from S. 19th to S. 15th St – southbound lane closure.
  • 25th Street from E. G St. to E. J St. – eastbound lane closure. 

More

  • Driveway and pedestrian access is maintained, although some sidewalks and crosswalks will be temporarily closed. Pedestrian detours will be in place.
  • Buses will follow detour routes. Visit org for information.
  • Construction noise related to removing pavement and operating equipment.
  • Large construction equipment or materials may be in the right-of-way.
  • Work will generally take place during the daytime hours unless otherwise noted. Daytime hours during the week are 7 a.m. to 9 p.m. The contractor usually works less hours.
  • Businesses are open during construction.
  • Plan ahead and allow extra time to reach your destination.
  • Due to inclement weather or unforeseen issues, dates and times are subject to change.

Contact us

Community Engagement: liz.ellis@soundtransit.org or 253-208-0586
After-hours construction hotline: 888-298-2395

More updates


Your safety is our priority

Learn how to stay safe around our construction sites.

Stay safe

24-hour construction hotline: 888-298-2395

More project info: soundtransit.org/htlink
Get in touch: liz.ellis@soundtransit.org or 253-208-0586