Starting environmental review
The alternatives development phase of the Everett Link Extension project wrapped up in June 2023, when the Sound Transit Board identified station, route, and Operations and Maintenance Facility (OMF) North location alternatives to study in the Environmental Impact Statement (EIS). We will be studying these alternatives through the environmental review phase of planning, which is expected to last through 2027.
What’s changed since our last engagement in spring 2023?
- Thanks to your input, we have narrowed down the station and route alternatives from what we shared with you during scoping in early 2023.
- We determined preferred alternatives for some portions of the project.
- The project team has advanced the design to incorporate some of the feedback we heard during scoping and to define the study area for environmental review.
- In early 2024, we will share more details about any changes and how the design is advancing.
|
|
Sound Transit staff speak with members of the public at the Lynnwood Luau on Aug. 19. Staff handed out materials, helped orient community members with the project map, and fielded questions from passersby.
Summer engagement recap
If you stopped by a summer festival or farmers market in Snohomish County this summer, you may have seen us out answering questions and letting people know that light rail is coming your way. We talked to over 2,000 community members at over a dozen events, including:
- Everett Farmers Market
- Everett Station District Town Hall Day
- Everett Pride
- Latino Expo
- Nubian Jam
- Sounds of Africa Festival
- Everett Food Truck Festival
- Connect Casino Road Carnival
- Lynnwood Luau
- Hand in Hand’s Mariner Fest
- ChildStrive’s Village Connection Fair
|
|
During environmental review, Sound Transit is coordinating with local governments and property owners throughout the project corridor to collect and analyze information necessary to understand potential effects of the project on the natural and built environment. As part of this process, crews will perform fieldwork such as: noise and vibration monitoring, geotechnical borings, archaeological investigations, and historic building surveys.
If you see crews doing fieldwork, please note that this does not necessarily mean that the properties being surveyed will be affected by the project; it just means that they are within the study area and will be included as part of our analysis. It’s early in the process, and we will publish our findings in the Draft EIS, anticipated for release in 2026.
We encourage you to follow us on Facebook, X (formerly known as Twitter), and Instagram @SoundTransit and forward email updates like this to family, friends, neighbors, and your community! Expanding light rail to Snohomish County is new for many community members, and we are trying to reach as many people as possible. Your voice matters and we hope that you stay engaged with this project as it moves forward.
We are happy to meet with community groups to provide more information about the project. Please reach out to us at everettlink@soundtransit.org to request a briefing. Follow Sound Transit on social media!
|
|
|
|