Work will begin at 11:00 PM and end at 2:30 AM each day. Please board all trains on the platform to Lynnwood City Center Station during this time.

Starting at 9:20 PM, trains will be running about every 15-20 minutes.

Please pay attention to in-station announcements and signage.

Affected direction: to Angle Lake

Affected stops:
Mount Baker (to Angle Lake)
Beacon Hill (to Angle Lake)
Construction work is taking place at the new Pinehurst Station. Trains will share one track through the Shoreline South/148th Station requiring passengers to use the alternate side of the platform during construction hours. Work will take place evenings, Monday through Friday, from 7 p.m. until 5 a.m., and all day on Saturday and Sunday. Trains will arrive about every 12 minutes beginning at 5:30 p.m.

Phase 1: March 24 through April 13 - Complete

Phase 2: April 28 through May 30 - Trains will be using the Angle Lake platform.

During the weekend of May 2-4 there will be construction in the area but it will not require the trains to share one track.

No work will be done May 17-18, and during the Memorial Day weekend of May 24-26