Pinehurst Station
Adding a station to the Lynnwood Link Extension

News and updates

Project update

Update: Rain delay for closures of northbound I-5 off-ramp; closures of NE 130th St and eastbound NE 130th St continue

Starting Friday, October 24, Sound Transit will continue to close eastbound NE 130th St going over the I-5 overpass. Access to eastbound Roosevelt Way NE from the 130th St off-ramp and 5th Ave NE…

Project update

Update: Closures of northbound I-5 off-ramp postponed; closures of NE 130th St and eastbound NE 130th St continue

Starting Monday, October 13, Sound Transit will continue to close eastbound NE 130th St going over the I-5 overpass. Access to eastbound Roosevelt Way NE from the 130th St off-ramp and 5th Ave NE…

Project update

Closures of northbound I-5 off-ramp to NE 130th St and eastbound NE 130th St

Starting Monday, October 13, Sound Transit will continue to close eastbound NE 130th St going over the I-5 overpass. Westbound NE 130th St over the I-5 overpass will remain open. There will be…

Project update

Northbound I-5 off-ramp to NE 130th St and eastbound NE 130th St closures

Starting Friday, Sept. 19, Sound Transit will close the northbound I-5 off-ramp to NE 130th St and eastbound NE 130th St going over the I-5 overpass. Westbound NE 130th St over the I-5 overpass will…

Project update

Closure extension for eastbound NE 130th St & upcoming full closure of NE 130th St

Sound Transit will extend the eastbound NE 130th St closure through Aug. 25 with the possibility of contingency extension through Aug. 29. Starting Saturday, Aug. 23, there will be a full closure of…

News release

Link 1 Line service will run every 12 minutes on evenings and weekends during Pinehurst Station construction

The Link 1 Line will experience slightly longer headways during some weekday evenings and weekends starting Monday, Aug. 11, to accommodate construction at the future Pinehurst Station. Trains will…

Project update

Update: Closure extension for eastbound NE 130th St

Starting Aug. 1, Sound Transit will extend the eastbound NE 130th St closure for two weeks. This closure will now end on Aug. 15. See maps for closure and detour information.

Project update

Extension of weekend closure: Eastbound NE 130th St

On Monday, July 28, eastbound NE 130th St going over the I-5 overpass will continue experiencing closures. The I-5 off-ramp at NE 130th street will re-open at 5 a.m. on that morning, and soon after,…

Project update

Long-term closure of northbound I-5 off-ramp to NE 130th St and eastbound NE 130th St

As early as Friday, July 11, the northbound I-5 off-ramp to NE 130th St and eastbound NE 130th St going over the I-5 overpass will continue experiencing closures. Westbound NE 130th St over the I-5…

Project update

Extension of weekend closure: Northbound I-5 off-ramp to NE 130th St and eastbound NE 130th St

As early as Friday, June 20, the northbound I-5 off-ramp to NE 130th St and eastbound NE 130th St going over the I-5 overpass will continue experiencing closures for the next 2 weekends. In addition…