Closure of South Bound Lanes on 112th Ave SE on Tuesday, October 6th 

Publish Date

Rain on Sunday morning caused crews to reschedule a portion of weekend paving work on 112th Ave SE to Tuesday, October 6th. Crews will be closing the south bound lanes of 112th Ave SE between SE 8th Street and Bellefield Park Lane. 

This work will be done under an extended work permit which allows crews to work between 6am and 6pm. Due to the nature of paving work, residents near the work site may be impacted by the noise of trucks and vibrations from the compaction of new pavement. 

Bellefield Residential residents and guests will need to access the park from the south, via Belleview Way SE. See below for more information. 

When

6 am – 6 pm Tuesday, October 6th 

Where

South bound lanes on 112th SE between Bellefield Park Lane and SE 8th Street.

More

  • Bellefield Residents and guests will be able to access the residential park from Bellevue Way SE. When leaving the park, residents will be able to travel north and south bound.
  • Detours:
    • From I-405 travel north on 112th Ave SE to Main Street. Turn left on Main Street and travel west to Bellevue Way. Turn left on Bellevue Way to travel south 
  • Plan ahead, leave early and allow extra time to reach your destination.
  • Due to inclement weather or unforeseen issues, dates and times are subject to change.