Cross passage restoration update
Publish Date
Body
Cross passage excavation at each underground location has been completed. Sound Transit and the contractor will meet, or have met, with the City of Seattle to discuss the final restoration where work was performed at the surface above these cross passages. The contractor will then develop a construction work plan to restore the area following the City of Seattle's direction.
The construction work plan will include:
- The area that will be restored in the public right of way
- Potential impacts to the street, vegetation, sidewalk, driveways and/or planter strips
What's next: We will provide a Construction Alert as notice of the expected restoration start date. This will include possible sidewalk, driveway, lane and/or street closures depending on the location.
Start date: Summer 2017
Work hours: 8 a.m. to 5 p.m. Monday – Friday
Duration: Summer – Mid to late Fall.