Hours extended for temporary lane closure at the Roosevelt Station site
Publish Date
Body
What
As early as Tuesday, Jan. 22, the temporary lane closure along the west side of 12th Avenue Northeast between Northeast 65th and Northeast 68th street will be closed 24/7. This is to allow the contractor to prepare the roadway for final restoration.
When
Tuesday, Jan. 22 – Friday, Feb. 8, 2019. Work hours: 7 a.m. to 5 p.m.
Where
Northbound lane along the west side of 12th Avenue Northeast between Northeast 65th Street and Northeast 68th Street (see map).
More
- Sawcut and demo road panels
- Replace road panels
- Pour sidewalks and curbs
- Plan ahead, leave early and allow extra time to reach your destination
- Due to inclement weather or unforeseen issues, dates and times are subject to change
Contact us
Outreach Specialist: Rhonda Dixon, northlink@soundtransit.org or 206-398-5300
After-hours construction hotline: 888-298-2395