Roosevelt Station - Early morning concrete pour

Publish Date
Body

The week of April 9th Sound Transit's contractor will conduct a large concrete pour requiring work to begin at 4 a.m. at the Roosevelt Station site. A temporary noise variance permit has been obtained from the City of Seattle for this work. The concrete pour is expected to take one day.

Map of construction area for concrete pour.

What to expect:

  • Traffic impacts: None, all work done on-site.
  • Construction activities: Setting up the concrete pump, trucks entering and exiting the site, tower crane moving equipment. The contractor will install sound barriers around the concrete operation to help keep noise to a minimum.
  • Equipment: Concrete pump truck, concrete trucks, tower crane.
  • Permitted start times: Setup as early as 4 a.m., pour as early as 5 a.m.

*Work is weather dependent. Notices will be resent for any schedule changes.