Project updates
Learn about where and when construction is happening throughout the ST district.

Traffic Revisions Coming: Jan. 15-16 & Jan. 19-21 at NE 100th St., NE 103rd St. & 1st Ave. NE

Publish Date
Body

This weekend (Jan. 15 and 16) and next week (Jan. 19 and 21), crews will be working on 1st Avenue NE at the NE 100th and NE 103rd street intersections.  The intersections will be intermittently closed to westbound traffic. Access to the NE 100th St. entrance to the Northgate Transit Center will be maintained. Flaggers and signage will direct vehicles around the work are

What to expect

Jan. 15 -16

  • Pavement cutting will start at 100th, Friday, Jan. 15, during the day. Excavation and storm line installation will continue through the night into the morning of Saturday, Jan. 16.
  • Pavement cutting will start at 103rd St. Friday, Jan. 15 from 8 p.m. – 10 p.m. Excavation will follow until 6 a.m. on Saturday, Jan. 16.

Jan. 19 -21

  • Pavement cutting will start at 100th from 8 p.m. – 10 p.m. Excavation will start after 10 p.m. and last through the day and night shift on January 20.
  • Pavement cutting will start at both 100th and 103rd St. Thursday, Jan. 21 from 8 p.m. – 10 p.m. Excavation will follow on 100th street during the night shift on Jan. 21.

Construction Activities:

  • Pavement sawing
  • Vacuum Trucks
  • Excavation
  • Pipe cutting
  • Paving