Utility work at NE 67th Street

Publish Date
Body

As soon as Wednesday, Feb. 18, Sound Transit's contractor will begin water line work in the corner of 12th Avenue NE and NE 67th Street.

Crews will typically work from 7 a.m. to 5 p.m. Monday through Friday. Parking will be closed 24-hours a day near the intersection to accommodate the work and to maintain traffic on 12th Avenue NE.

This work is expected to take approximately three to five weeks to complete, depending on weather.

During working hours, you can expect:

  • Pavement sawing
  • Excavation
  • Pipe cutting
  • Paving

 