Extension: Nightly Closure of 46th Ave W

updated 10/03/2022: This work has been extended to take place until 10/13, with the same hours (Mon-Thurs, 10 pm - 5 am) As early as Monday, August 22, Sound Transit’s contractor will work at…

Nightly Closure of 46th Ave W

As early as Monday, July 18, Sound Transit’s contractor will work at the direct access on and off ramps at 46th Ave W. This work will require the closure of the direct access on and off ramps to the…

Interurban Trail Construction

As early as June 20, Sound Transit’s contractor will be working at the Interurban Trail near 44th Ave W to complete stream construction. Work will be conducted at night from June 20 – June 24, from 7…

Correction: 46th Ave W Closure

As early as Monday, June 20, Sound Transit’s contractor will work at the direct access on and off ramps at 46th Ave W. This work will require the closure of the direct access on and off ramps to the…

Parking lot shifts at Lynnwood Transit Center (LTC)

As early as June 13, Sound Transit’s contractor will close off sections of the Lynnwood Transit Center parking lot for continued construction activities to complete the improvements for the Lynnwood…

Westbound Right Lane Closure of 236th St SW

From Monday, May 30 to Friday, September 2, Sound Transit’s contractor will work at 236th St SW westbound between the on-ramp to I-5 southbound and 59th Pl W for installation of a retaining wall and…

Closure of I-5 northbound for night work

As early as Friday, May 20 through Monday, May 23, Sound Transit’s contractor will close the I-5 northbound lanes from 11 PM – 6 AM and traffic will be detoured to perform work for the Lynnwood Link…

Closure of I-5 Southbound for night work

As early as Friday, May 13 through Monday, May 16, Sound Transit’s contractor will close the I-5 Southbound lanes from 11 PM – 6 AM and traffic will be detoured to perform work for the Lynnwood Link…

Portion of the Interurban Trail near Lynnwood Transit Center to reopen on May 1

After being closed for nearly ten months, the portion of the Interurban Trail between 52nd Ave. W and 44th Ave. W near the Lynnwood Transit Center will reopen on Sunday, May 1. The section of the…

Interurban Trail connection re-opens May 1; Scriber Creek Trail remains closed until fall

A portion of the Interurban Trail near the Lynnwood Transit Center will be restored beginning Sunday, May 1, removing the detour in place for Interurban Trail users for the past 10 months.