Voter approval (2016)
-
Milestone Target Alternatives development Board identifies preferred and other Draft EIS alternatives Draft Environmental Impact Statement Board confirms or modifies the Preferred Alternative Final Environmental Impact Statement Board selects project to be built Federal Record of Decision -
Alongside the design milestones below, the WSLE project team is actively working to identify cost-savings opportunities.
Milestone Final route design Final station designs Procure and commission station and public art Obtain land use and construction permits Property acquisition/relocation -
Construction of WSLE is scheduled to begin in 2027, with start of service targeted for 2032. See below for more information.
Milestone Groundbreaking Construction updates and mitigation Safety education Testing and pre-operations -
Start of service, 2032