Construction activities coming to Downtown Redmond

Publish Date

Beginning as early as Monday, Feb. 8, Sound Transit’s contractor crews will begin preparing designated construction areas from 164th AVE NE to 170th AVE for upcoming construction activities.

What

Contractor crews will begin tree and vegetation removal and installation of construction fencing within designated construction areas.

Where

164th Avenue Northeast to 170th Avenue.

When

Monday, February 8, 2021- ongoing

More

Construction activities will include:

  • Construction fencing and signage.
  • Tree and vegetation removal.
  • Parking restrictions.
Construction map for 164th Ave NE to 170th Ave tree removal, Downtown Redmond Link Extenstion