Project updates
Learn about where and when construction is happening throughout the ST district.

Early morning concrete pour on Northgate guideway

Publish Date

Starting Tuesday morning, July 16th, Sound Transit's contractor will be pouring concrete foundations for the guideway's switches and crossover tracks.

What

Early morning concrete pours on guideway.

When

Beginning Tuesday, July 16th these concrete pours will occur two to three days per week until the week of August 5th, 5 a.m. – 8:30 a.m.

  • 5 a.m. – 6 a.m.: Concrete pump trucks will begin set-up
  • 6 a.m. – 8:30 a.m.: Concrete pour

Where

Concrete pour will occur at two locations on the guideway: one North of the station near the end of the guideway and one South of the station (see map).

More

  • A Temporary Noise Variance (TNV) has been issued by the City of Seattle for this work.
  • Construction equipment includes concrete and pump trucks.
Map of traffic impacts for concrete pour.

 

Contact us

Outreach Specialist: Alexis Lair, northlink@soundtransit.org or 206-398-5300
After-hours construction hotline: 888-298-2395