Nighttime work for track slab delivery and installation

Publish Date
Body

What
Sound Transit’s contractor will receive delivery of track slabs for the trackway in the U District Station site. Once deliveries have been made they will then install the slabs. There will be minimal traffic impacts. This nighttime work is covered under the Major Public Project Construction Noise Variance (MPPCNV). 

When
Track Slab Delivery and Installation: 
Monday- Friday 8:00 p.m. – 6:00 a.m.  Beginning December 17 and continuing until complete in late January.

Where
Brooklyn Ave NE between NE 45th and NE 43rd Street

South gate: Trucks will enter on Brooklyn Ave NE near NE 43rd Street. Once the trucks have been emptied they will leave the site through the North gate and proceed down to NE 50th Street before entering the freeway (see map). 

More

  • On site crane will be used to pick up slabs off delivery trucks and lower them into the station for installation.
  • There will be two trucks a night that will pull into the site.
Track slab truck routes