Utility work around the Maple Leaf Portal site

Publish Date
Body

In the next several weeks you will begin to see utility work to prepare for the excavation of the Maple Leaf Portal for the Northgate Link Extension. Work will begin as early as April, take place in three phases and be completed no later than July 2013. 

Phase 1: Seattle City Light (SCL) will relocate poles and overhead power lines from the west to the east side of 1st Ave NE between NE 92nd and NE 97th Street. This relocation work must be done to maintain power to customers and meet standards for distances between power lines and the light rail portal.

Phase 2: Century Link will relocate overhead phone lines from the west side of 1st Ave onto the new SCL poles. They will then remove poles and abandoned overhead phone lines along the west side of 1st Ave NE between NE 97th and NE 100th Street.

Phase 3: Comcast will relocate existing overhead cables from the west side of 1st Ave NE onto the new SCL poles along the eastside of 1st Ave NE. 

This update reflects the best information about the schedule that is currently available; the dates are preliminary and subject to change. Additional updates will be distributed as more information including key dates that become available. 

More information

For information about Seattle City Light utility work, please contact Steve Byers, Senior Capital Projects Coordinator, at 206-684-3637 or stephen.byers@seattle.gov. You can also visit the Seattle City Light construction website. 

For information about the Northgate Link Extension, including the Maple Leaf Portal, contact Rhonda Dixon, Community Outreach Specialist: 206-398-5300 or northlink@soundtransit.org.