Announcement
Ongoing
In effect: April 30 - May 2
Routes:
1 Line
Handrails for the public stairwells will be extended at both the top and bottom. This will be completed in three phases. Passengers will need to use the elevators and alternate stairs.
Phase 1: The south plaza stairs to the northbound and southbound plaza. Access to the northbound and southbound platforms will be available from the south plaza elevators and the north/overcrossing stairs and elevators.
Phase 2: During welding at the top of the north/overcrossing stairs (expected duration 4 hours): the north/overcrossing to the northbound and southbound platforms and ped bridge from garage to overcrossing will be closed. Access to the southbound platform will be from the garage stairs or south plaza stairs and elevator.
Phase 3: During welding at the bottom of the stairs; the north/overcrossing stairs to the northbound and southbound plaza will be closed. Overcrossing will be opened. Access to the northbound and southbound platforms will be available from the north/overcrossing elevators and south plaza stairs and elevators.
Work will be done sequentially. Access to the southbound platform will not be impacted until after the morning commute.
Affected lines:
1 Line