Night closure of northbound I-5 right lanes and coinciding ramp closures

Starting Monday, March 4, Sound Transit will close the northbound I-5 on-ramp from NE 175th St, the right lane of northbound I-5 between NE 175th St and NE 200th St, and the northbound I-5 off-ramp…

Nightly lane restrictions on NE 145th St (WA-523)

Continuing Sunday, March 3, Sound Transit will be performing waterline work causing nighttime lane restrictions on both eastbound and westbound NE 145th St (WA-523) from 3rd Ave NE to 8th Ave NE. The…

Night work along I-5 in Mountlake Terrace

As early as Friday, March 1, Sound Transit’s contractor will perform night work on I-5 in Mountlake Terrace. This work will include median filter drain installation, metal beam guardrail installation…

Nightly closure of northbound I-5 on-ramp, off-ramp, and right lane

As early as Monday, Feb. 26, Sound Transit will close the northbound I-5 on-ramp at NE Northgate Way, the right lane on northbound I-5 from NE Northgate Way to NE 130th St, and the northbound I-5 off…

Full closure of 46th Ave W

As early as Monday, Feb. 26, Sound Transit’s contractor will continue working on pavement markings at 46th Ave W. This will require the closure of 46th Ave W south of 200th St SW and the HOV ramp…