2. Timeline and milestones

  • Voter approval (2016)

  • Milestone Target
    Alternatives development 2018 - 2019
    Board identifies sites for further study in the Draft Environmental Impact Statement 2019
    Draft Environmental Impact Statement 2019 - 2020
    Board confirms or modifies the preferred site options 2020
    Final Environmental Impact Statement 2020 - 2021
    Board selects project to be built 2021
  • Milestone
    Final facility design
    Procure and commission facility and public art
    Obtain land use and construction permits
    Property acquisition/relocation
    Groundbreaking
    Construction updates and mitigation
    Safety education
    Testing and pre-operations
  • Open for operations (2026)