-
Voter approval (2016)
-
Milestone Target Alternatives development 2018 - 2019 Board identifies sites for further study in the Draft Environmental Impact Statement 2019 Draft Environmental Impact Statement 2019 - 2021 Board identifies a preferred site alternative 2021 Final Environmental Impact Statement 2022 Board selects project to be built 2022 -
Milestone Final facility design Procure and commission facility and public art Obtain land use and construction permits Property acquisition/relocation Groundbreaking Construction updates and mitigation Safety education Testing and pre-operations -
Open for operations (TBD)
*With greatly depleted revenues from COVID-19, Sound Transit will not be able to deliver many expansion projects on their original timelines. Through a program realignment between now and summer 2021, the Sound Transit Board of Directors is working to determine which plans and timelines for voter-approved projects will need to change due to lower revenue projections, absent receiving alternative revenue. These discussions could affect the schedule milestone and opening dates for OMF South.