Shoreline South/148th Station
Connecting to new SR 522/NE 145th BRT.

News and updates

Project update

Off-Ramp night closure at Northbound Interstate-5 to Northeast 145th Street Exit 175

Beginning Monday, October 25th, Sound Transit will be closing the off-ramp from NB I-5 via exit 175 for construction of the Lynnwood Link light rail.

Project update

Night time road closure on 5th Ave NE and NE 130th Street overpass and off-ramp

As early as October 18th, Sound Transit’s contractors will work on 5th Ave NE and NE 130th Street overpass and off-ramp for guideway construction as part of the future link light rail.

Project update

Night time full closure at NE 155th Street from 1st Ave to 5th Ave

As early as October 18th, Sound Transit will begin a full closure at NE 155th Street for girder delivery and guideway work.

Project update

Night time closure at NE 145th on-ramp to Northbound I-5

Beginning, October 18th, Sound Transit will closure the NE 145th on-ramp to NB I-5 for guideway construction.

Project update

Night time closure at NE 130th off-ramp from Northbound I-5

As early as Sunday, October 17th, Sound Transit will close the NE 130th Street off-ramp from NB I-5 for guideway construction.

Project update

Rescheduled work: Alternating lane closure at NE 185th Street and 5th Ave overcrossing

This work has been rescheduled to Oct. 19th. Sound Transit will be alternating lane closure at Northeast 185th Street and 5th Avenue for pothole work.

Project update

Night time closure at NE 130th off-ramp from northbound I-5

As early as Sunday, Oct. 10th, Sound Transit will close the Northeast 130th Street off-ramp from northbound Interstate 5 for guideway construction.

Project update

Extended full closure at NE 145th overcrossing and NB I-5 NE 145th Street exit 175

This work will be extended to October 14th. Sound Transit will be closing the off-ramp from NB I-5 via exit 175 for work zone for girder setting. Additionally, there will be a full closure at the NE…

Project update

Extended full road closure on NE 125th Street from 5th Ave to 8th Ave for concrete panel

Sound Transit is extending this full closure at NE 125th Street from 5th Ave to 8th Ave for concrete panel pouring. The work will be extended to Saturday, October 9th.

Project update

Full closure at NE 145th overcrossing and NB I-5 NE 145th Street exit 175

As early as Wednesday, September 29th, Sound Transit will be closing the off-ramp from NB I-5 via exit 175 for work zone for girder setting. Additionally, there will be a full closure at the NE 145th…