-
Voter approval (2016)
-
Milestone Year Alternatives development 2018 - 2019 Board identified preferred alternative 2019 Draft Environmental Impact Statement 2024 Board confirms or modifies the Preferred Alternative 2025 Final Environmental Impact Statement 2027 Board selects project to be built 2027 Federal Record of Decision 2027 -
Milestone Final route design Final station designs Procure and commission station and public art Obtain land use and construction permits Property acquisition/relocation -
Milestone Groundbreaking Construction updates and mitigation Safety education Testing and pre-operations -
*As part of the Enterprise Initiative, the Board has deferred station parking until additional funding sources are identified.
Tacoma Dome Link Extension
Connecting Tacoma and Fife to regional light rail