2. Timeline and milestones

  • Voter approval (2016)

  • Milestone Target
    Alternatives development 2017 - 2019
    Board identifies preferred alternative 2019
    Draft Environmental Impact Statement 2019 - 2021
    Board confirms or modifies the Preferred Alternative 2021
    Final Environmental Impact Statement 2021 - 2022
    Board selects project to be built 2022
    Federal Record of Decision 2022
  • Milestone
    Final route design
    Final station designs
    Procure and commission station and public art
    Obtain land use and construction permits
    Property acquisition/relocation
  • Milestone
    Groundbreaking
    Construction updates and mitigation
    Safety education
    Testing and pre-operations
  • Start of service (2030)