Tacoma Dome Link Extension
Connecting Tacoma and Fife to regional light rail

Timeline and milestones

  • Voter approval (2016)

  • MilestoneYear
    Alternatives development2018 - 2019
    Board identified preferred alternative2019
    Draft Environmental Impact Statement2024
    Board confirms or modifies the Preferred Alternative2025
    Final Environmental Impact Statement2027
    Board selects project to be built2027
    Federal Record of Decision2027
  • Milestone
    Final route design
    Final station designs
    Procure and commission station and public art
    Obtain land use and construction permits
    Property acquisition/relocation
  • Milestone
    Groundbreaking
    Construction updates and mitigation
    Safety education
    Testing and pre-operations
  • *As part of the Enterprise Initiative, the Board has deferred station parking until additional funding sources are identified.