Girder placement

From Tuesday, July 10 until Saturday morning, July 14, crews working to build Sound Transit’s East Link project will install concrete girders between future elevated guideway columns in Redmond’s Overlake neighborhood. Mobile cranes will be at work along SR 520 at 148th Avenue NE from 10 p.m. to 5 a.m. nightly.

Ramp and street closure schedule

  • Tuesday, July 10 – Wednesday, July 11 - The 148th Street on-ramp to eastbound SR 520 will be closed from 10 p.m. to 5 a.m. nightly
  • Tuesday, July 10 – Friday, July 13 - The eastbound SR 520 exit ramps to 148th Avenue NE will be closed from 10 p.m. to 5 a.m. nightly
  • Wednesday, July 11 – Friday, July 13 - 148th Avenue NE at SR 520 from 10 p.m. to 5 a.m.