Project updates
Learn about where and when construction is happening throughout the ST district.

Looking forward

Publish Date
Body

The Link Operations & Maintenance Satellite Facility (OMSF) site alternatives have been identified and environmental review is underway. The Draft Environmental Impact Statement (DEIS) is anticipated in mid-2014. Once released, a public review and comment period will begin. Public comments will be collected and the Sound Transit Board of Directors will review all the information prior to identifying a Preferred Alternative for the OMSF.

Site alternatives identified (2013)
Environmental review (2013-2014)
Record of Decision & permitting (2015)
Construction (2016-2020)
Targeted project completion 2020

What's next?

In mid-2014 Sound Transit will complete and publish the OMSF Draft Environmental Impact Statement (DEIS) for your review. Local communities and project stakeholders will be invited to formally comment on the Project and DEIS.

The Sound Transit Board will consider comments recorded online and at public hearings in Bellevue and Lynnwood.