Voter approval (2016)
-
Milestone Target Alternatives development Board identified preferred and other WSBLE Draft EIS alternatives WSBLE Draft EIS and public comment period Environmental review for the WSLE and BLE projects proceed on different timelines BLE National Environmental Policy Act (NEPA) scoping We are here BLE Draft Environmental Impact Statement and public comment period 2026 ST Board confirms or modifies the BLE Preferred Alternative 2026 BLE Final Environmental Impact Statement publication 2026 ST Board selects BLE project to be built 2026 -
BLE is scheduled to begin design after the Federal Record of Decision. At this time, we are working with our federal partners to understand the timeline of our outgoing environmental review phase for the BLE. The BLE project timeline will be updated when additional information is available.
Milestone Procure final design and construction contracts Obtain land use and construction permits Begin property acquisition/relocation Advance utility relocation/early work contracts -
BLE is scheduled to begin construction and testing in 2028, concluding in 2039. The start of services for BLE is scheduled for 2039. See below for more information. Note that construction for the project between Smith Cove and Ballard stations will begin as funding is available.
Milestone Demolition and clearing where necessary to build and operate the light rail guideway Earth work such as stormwater systems, column footings, retaining walls and tunneling Guideway and station construction Ongoing conversations with anyone affected by construction Safety education Testing and preparations -
Note that all dates are anticipated and will be updated as new information is available.