First powered light rail vehicle crosses I-90 floating bridge

The first Link light rail vehicle crossed the I-90 floating bridge under its own power Monday night, enabling the start of a series of tests to prepare for the opening of the full 2 Line in early…

People in protective gear walk next to a Link light rail vehicle on the I-90 bridge during an unpowered tow test.

The Platform

Introducing our new series: Crosslake Update

In our May blog on the 2 Line’s Crosslake Connection across Lake Washington, we shared an update on remaining construction activities and video of a thrilling testing milestone: the first light rail…

A drone shot of the I-90 bridge on a sunny day.

The Platform

Spring construction update: The 2 Line’s crosslake connection

On May 10, thousands of eager riders turned out to celebrate opening day of the new 2 Line extension to Downtown Redmond. It was a great moment for the city and the entire Eastside, and throughout…

Project update

Work to begin on Mercer Island East Link Traffic Mitigation Project

As part of the Environmental Impact Study and Record of Decision for the East Link Light Rail project, Sound Transit will make traffic mitigation efforts around the Mercer Island station. The…

News release

Light rail opens on the Eastside

Starting this morning, passengers on the Eastside will be able to use Link light rail to travel quickly and safely to destinations throughout Bellevue and Redmond. The 6.6-mile initial segment of the…

Project update

2 Line Fire Alarm Testing in Bellevue Tunnel

As part of 2 Line simulated service, crews will be running drills to test fire alarm equipment at the Downtown Bellevue Station and Bellevue Tunnel.  

Project update

Simulated 2 Line service to begin — Expect to see trains every 10-15 minutes, including at street crossings

Since civil construction has finished, test trains will begin running on the 2 Line between South Bellevue Station and Redmond Technology Station every 10–15 minutes as part of preparation for…

Project update

Ongoing construction at South Bellevue Station and Spring District Station

As we prepare to open 2 Line service between eight East Link Extension stations in early 2024, Sound Transit crews will be operating on a 24-hour basis.

Project update

Ongoing construction at South Bellevue Station

Sound Transit crews will be working expanded hours at South Bellevue Station to complete waterproofing, tile work, and site furnishings in preparation for the 2 Line service opening between eight…

Project update

Closure of westbound I-90 HOV ramp at 80th Ave SE

Starting as soon as Thursday, Oct. 12, Sound Transit crews will close the westbound I-90 HOV ramp between SE 27th Ave and 80th Ave SE. The closure will take place from 9 p.m. to 5 a.m. the following…