Project update
Military Road S ongoing roadway restoration activities
Starting Friday, July 18, Sound Transit’s contractors will mill and pave Military Road S, which requires overnight closures, directional closures, and daytime flagging. This work is needed to restore…
Project update
Nighttime closures of downtown Federal Way surface streets and I-5 southbound off-ramp to South 320th St
Starting Monday, July 21, through Thursday, July 24, Sound Transit’s contractor crews will close several roadways overnight in downtown Federal Way. These closures are necessary to complete roadway…
Project update
Nighttime lane closure on westbound S 272nd St
Sound Transit’s contractors will close both lanes of westbound S 272nd St, where it meets Pacific Highway S, at night starting on Monday, July 21, for nine days. This closure is for expanding the…
Project update
Daytime closure of southbound right lane on 23rd Ave S
Sound Transit’s contractors will conduct a single right lane closure of southbound 23rd Avenue S between S 317th Street and S 320th St. Beginning as early as Monday, July 14 for approximately 5 weeks…
Project update
Parking Lane Closure on Northbound 21st Avenue S
Sound Transit’s contractors will close the sidewalk and parking lane along northbound 21st Ave S between S 320th St to S 318th St for approximately five weeks. This closure is necessary to complete…