News and updates

Project update

HOV ramp closures at Island Crest Way

The Island Crest Way westbound I-90 HOV on-ramp and the eastbound I-90 HOV off-ramp are scheduled to be closed Wednesday, Dec. 4 from 9 a.m. – 3 p.m. Crews will be pouring concrete for curbs and…

Project update

HOV ramp closures at Island Crest Way

The Island Crest Way westbound I-90 HOV on-ramp and the eastbound I-90 HOV off-ramp are scheduled to be closed Monday, Nov. 25 – Tuesday, Nov. 26 from 9 a.m. – 3 p.m. Crews will be pouring concrete…

Project update

HOV ramp closures at Island Crest Way

The Island Crest Way westbound I-90 HOV on-ramp will be closed Tuesday, Nov. 19 – Thursday, Nov. 21 from 9 a.m. – 3 p.m., and the Island Crest Way eastbound I-90 HOV off-ramp will be closed Wednesday…

Project update

HOV ramp closures at Island Crest Way

The Island Crest Way westbound I-90 HOV on-ramp and the Island Crest Way eastbound I-90 HOV off-ramp will be closed on Wednesday, Nov. 13 from 9 a.m. – 3 p.m. Crews will be pouring concrete for curbs…

Project update

I-90 HOV ramp closure at Island Crest Way

The Island Crest Way westbound HOV on-ramp will be closed on Monday, Nov. 4 and Tuesday, Nov. 5 from 9 a.m. – 3 p.m. Crews will be pouring concrete for curbs and sidewalks at Mercer Island…

Project update

HOV ramp closure at Island Crest Way

The Island Crest Way westbound HOV on-ramp will be closed on Monday, Oct. 28 and Tuesday Oct. 29 from 9am – 3pm. Crews will be pouring concrete for curbs and sidewalks at Mercer Island Station.…

Project update

I-90 ramp closure at Island Crest Way

The Island Crest Way westbound HOV on-ramp will be closed Monday, Oct. 21, from 9 a.m. – 3 p.m. Crews will be pouring concrete at the Mercer Island Station platform. During this closure, drivers can…

Project update

Overnight work at Shorewood Drive: Oct. 22 and 23

Beginning as early as Tuesday, Oct. 22, the first traction power substation (TPSS) will arrive on Mercer Island and will be installed at Shorewood Dr. and I-90. TPSS units provide electricity to the…

Project update

80th Ave. eastbound HOV ramp closure: Oct. 9 - 18

Beginning as early as Oct. 9, crews working for Sound Transit will close the 80th Avenue eastbound HOV on-ramp during off-peak hours to install new electrical conduit and new light fixtures. Sound…

Project update

I-90 ramp closure rescheduled

The planned closures for the Island Crest Way westbound HOV on-ramp, originally scheduled for this week, have been rescheduled for the week of Oct. 7 – 11. Crews will continue concrete pours for…