4. News and updates

Northgate Link construction reaches 70 percent completion

Sound Transit's Northgate Link Extension has reached 70 percent completion, as project construction move ahead to start service in 2021. The project is a major component of Sound Transit's regional…

Sparks fly inside the future underground Roosevelt Station

Fresh pics: Going underground at Roosevelt Station

Wouldn't it be nice to have a train from Northgate to UW, downtown Seattle and the airport during all of this #Viadoom business? It's in the works!  The Northgate Link light rail extension is about…

Hours extended for temporary lane closure at the Roosevelt Station site

What As early as Tuesday, Jan. 22, the temporary lane closure along the west side of 12th Avenue Northeast between Northeast 65th and Northeast 68th street will be closed 24/7. This is to allow the…

Night-time closure of portion of Northeast 103rd Street

On Tuesday, Wednesday, and Thursday night (1/22-1/24) continuing Friday night (1/25) through Saturday evening (1/26), Northeast 103rd Street between 1st Avenue Northeast to 3rd Avenue Northeast will…

Removal of temporary bridge abutments

What Sound Transit's contractor will remove temporary concrete structures to five feet below finish grade in front of U Manor Apartments to prepare for the re-installation of the street and sidewalk…