Project update
Extended full closure at NE 145th overcrossing and NB I-5 NE 145th Street exit 175
As early as Monday, November 22nd, Sound Transit will be closing the off-ramp from NB I-5 via exit 175 for work zone for girder setting. Additionally, there will be a full closure at the NE 145th…
Project update
Extended full closure at NE 145th overcrossing and NB I-5 NE 145th Street exit 175.
As early as Monday, November 15th, Sound Transit will be closing the off-ramp from NB I-5 via exit 175 for girder setting. Additionally, there will be a full closure at the NE 145th overcrossing.…
Project update
Night time closure at NE 130th off-ramp from Northbound I-5
As early as Monday, November 15th Sound Transit will close the 130th off-ramp.
Project update
Night closure at 1st Ave NE from NE 112th to NE 117th Street
Monday, November 8th, Sound Transit will be closing NE 1st Ave NE from NE 112th to NE 117th Street. The full night time closure will be utilized to set girders. This closure will take place between…
Project update
Cancelled: One lane road with alternating traffic on Northeast 155th Street between 1st Ave NE to 2nd Ave NE
*The extended work on NE 155th St. which was scheduled to occur from Monday 11/8 – Thursday 11/11 is postponed for a future date which has yet to be determined.
Project update
Night ramp closures at NE 145th Street and 5th Ave NE
As early as, November 1st, Sound Transit will be closing the on-ramp to NB I-5. Additionally, the off-ramp from NB I-5 to NE 145th will be closed for construction of the Lynnwood Link light rail.
Project update
Night time road closure on 5th Ave NE and NE 130th Street overpass and off-ramp
As early as Nov. 2nd, Sound Transit's contractors will work on 5th Avenue Northeast and Northeast 130th Street overpass and off-ramp for guideway construction as part of the future link light rail.
Project update
Night time closure at NE 130th off-ramp from northbound I-5
As early as Sunday, Nov. 1st, Sound Transit will close the Northeast 130th Street off-ramp from northbound Interstate 5 for guideway construction. Additionally, 5th Avenue will be closed from…
Project update
Extended work at NE 116th bicyclist/pedestrian trail closure
Sound Transit is extending the work at the Northeast 116th Street bicyclist/pedestrian path to construct the Lynnwood Link Extension light rail guideway.
Project update
Off-Ramp night closure at Northbound Interstate-5 to Northeast 145th Street Exit 175
Beginning Monday, October 25th, Sound Transit will be closing the off-ramp from NB I-5 via exit 175 for construction of the Lynnwood Link light rail.