News and updates

Alarm testing at the U District Station June 3-5

In preparation for station opening in 2021, Sound Transit's contractor at the U District Station site will test the alarm system on June 3-5. Nearby neighbors and passersby may hear intermittent…

Work extended: Restoration of Brooklyn Ave NE between NE 45th and NE 43rd Street

On Thursday, May 14, Sound Transit's contractor will continue the restoration of Brooklyn Avenue Northeast between Northeast 45th and Northeast 43rd Streets (see map). Within the work limits, the…

Restoration of Brooklyn Ave NE between NE 45th and NE 43rd Street 

Thursday, April 23, Sound Transit’s contractor will continue the restoration of Brooklyn Ave NE between NE 45th and NE 43rd Street (see map). Within the work limits, the contractor will demolish and…

Temporary sidewalk closures on NE 43rd St and Brooklyn Ave NE

Starting as early as Wednesday, March 11, Sound Transit's contractor will replace portions of sidewalk on both Northeast 43rd Street and Brooklyn Avenue Northeast. Crews will demolish and remove the…

Pedestrian path closing and construction sound wall removal around the U District Station site

What As early as Wednesday, January 15th, the pedestrian path around the U District Station (UDS) site will be permanently closed. Once the pedestrian path closes, Sound Transit’s contractor will…