Project update
NE 195th Street pedestrian bridge underground utility installation
As early as Monday, Aug. 24th Sound Transit will begin underground utility installation work at the Northeast 195th pedestrian bridge for light rail construction. What Sound Transit will be…
Project update
Shuttle service between Mountlake Terrace Transit Center and Roger’s Market suspended
The shuttle service between MLT TC and Roger’s Market is suspended until further notice. Riders can catch Community Transit bus routes 119, 130, 810 or 817 instead. What Shuttle service suspended…
Project update
Full closure of SR 104
As early as Wednesday, Aug. 12, Sound Transit's contractor will close State Route 104 for crane and equipment mobilization. Both the on and off ramps will be closed during nighttime work hours.…
Project update
Four month closure of 52nd Ave W between 208th St SW and 212th St SW
As early as Monday, Aug. 24th, Sound Transit's contractor will close a portion of 52nd Avenue West between 208th Street Southwest and 212th Street Southwest for approximately four months. During this…
Project update
Nighttime closures of off-ramp to westbound State Route 104 and off-ramp to SR 104 eastbound
As early as Monday, July 20, Sound Transit's contractor will continue night work at the State Route (SR) 104 and northbound Interstate 5 interchange. Both the off-ramps and on-ramps will be closed…
Project update
Off-ramp to westbound SR 104 and off-ramp to SR 104 eastbound closed
As early as Sunday, June 28, Sound Transit's contractor will continue night work on the off-ramp to westbound State Route 104 and the off-ramp to SR 104 eastbound. Both the off-ramps will be closed…
Project update
Mountlake Terrace Freeway Station to close for construction
As a part of ongoing Lynnwood Link Extension construction, the freeway station located at the Mountlake Terrace (MLT) Transit Center serving Community Transit Routes 410, 413, 415, 435 and Sound…
Project update
Saturday closure of Mountlake Terrace bus loop
As early as Saturday, June 13, Sound Transit’s contractor will close the bus loop at the Mountlake Terrace (MLT) Transit Center in order to prepare for guideway construction of the Lynnwood Link…
Project update
Seattle City Light work for drilled shafts
As early as Monday, June 8, Seattle City Light (SCL) will assist Sound Transit's contractor with work that will support the construction of the guideway for the Lynnwood Link Extension. The SCL work…
Project update
Heavy equipment mobilization
As early as Wednesday, June 3, Sound Transit's contractor will be mobilizing a crane across 220th Street Southwest in order to begin the installation of foundations and columns for a section of the…