2. Timeline and milestones

  • Milestone Target
    Project refinement 2018 - 2019
    Board advances refined project 2019
    Conceptual engineering 2019
    Environmental review (SEPA checklist) 2019 - 2020
    Board selects project to be built 2020
    Preliminary engineering 2020
  • Milestone
    Final route design
    Final stations designs and public art
    Obtain land use and construction permits
    Property acquisition and relocation
  • Milestone
    Groundbreaking
    Construction updates and mitigation
    Construction of roadway improvements, parking and stations
  • Start of service (2024)